West Wiltshire District Council
Bradley Road
Trowbridge
Wiltshire
BA14
0RD
Telephone: 01225 776655
Building Control Guidance Note
Drainage
and waste disposal (Part H)
New Regulations
(Issued - 09/05/02)
This guidance note highlights the main changes to
the Building Regulations relating to the Drainage and waste disposal - Approved Document H, which came
into force on the 1 April 2002. We can only attempt to deal with the key changes, so in the case of
any doubt or dispute, please refer directly to the Building (Amendment) Regulations 2001 and Approved
Document H for a definitive statement of the law.
Foul
Water Drainage - H1
Wastewater Treatment Systems and Cesspools
-H2
Rainwater Drainage - H3
Building
Over Sewers - H4
Separate Systems of Drainage - H5
Solid
Waste Storage - H6
Foul
Water Drainage - H1
The regulations now establish a priority order in
which methods of foul water drainage must be used. In each case the requirement is that the first method
on the list will be used - unless it is not "reasonably practicable" to do so, when the next
method must be used (and so on). For example, the Building Regulations will not now allow the installation
of a septic tank unless it can be demonstrated that it would not be "reasonably
practical" to connect to a public sewer or a private sewer.
Order
of priority
- A public sewer
- A
private sewer
- A Septic tank or treatment system
- A
Cesspool
Sanitary Pipework
- Cages
fitted to the top of Soil and Vent pipes must be metal in areas with rodent control problems
- WC
pipework should not allow light through (as it encourages damage by rodents)
- Boiler
condensate may connect to sanitary pipework - pipes to be min 22mm dia with 75mm trap.
- Rodding
points installed in Soil stacks must be above the spillover level of the lowest connected appliance.
Foul Drainage
- Includes
all foul pipework up to the point of connection with the sewer/septic tank etc - which clarifies the
position with regard to pipework put in at the same time as the sewer. For example, pipework from the
sewer to the back of the highway (to allow for future connections) will require Building Regulation
consent/inspection.
- Pipework serving more than 10 dwellings must be 150mm
diameter or greater.
- Drains serving hot food premises must have grease separators.
- Drains connecting into existing pipework (other than at a manhole) must use
prefabricated units to avoid the use of "saddles". Where the use of a saddle is unavoidable,
the hole in the existing pipe must be drilled - not broken out.
- New provisions
are introduced to limit the effects of surcharging drains - to prevent the foul sewage entering properties
(particularly basements) in the event of flooding etc .
- When planning the
drainage layout for new developments, private (ie drains that serve more than one property) and public
sewers must be positioned so as to make reasonable allowance for the possibility of future extensions
without needing to build over the sewer.
- Drains passing through walls must
either use "Rocker pipes" or the hole around the drain must be filled with compressible material
(in addition to the rigid sheet material already required each side).
- Rodent
control must be taken into account on re-developed sites. This may include sealed inspection chambers,
intercepting traps, specialist rodent barriers and solid gully covers.
- Where
both foul and surface water sewers are available, all connections made on site must be proved
to connect to the right one.
Wastewater
treatment systems and cesspools - H2
Septic
Tanks and Cesspools
- Septic tanks must have
a minimum capacity of 2700 litres ( 4 people ) - plus 180 litres for each extra person.
- Cesspools
must have a minimum capacity of 18,000 litres ( 2 people ) - plus 6,800 litres for each extra person.
- Both must be sited at least 7m from the habitable part of any building (preferably
downslope), within 30m of a suitable tanker access and be capable of being emptied without the need
for the hose to pass through the building.
- A notice must be provided within
the building describing the system, emptying details and legal responsibilities.
- The
revised regulations now cover the outfall drainage from septic tanks - must be 15m from any building,
10m from any watercourse, away from soakaways etc and not covered by drives, roads or paved areas. The
outfall drainage system must be designed following a percolation test, and is likely that consent from
the Environment Agency will also be required.
Packaged
Treatment Plants
- Must be type tested in accordance
with BS 7781 - and if it is electrically powered, it must be able to function adequately for 6 hours
without power (or have a backup power supply)
- The discharge must be at least
10m away from watercourses or buildings
- A notice must be provided within the
building describing required maintenance and legal responsibilities
Constructed
Wetlands/ Reed Beds and Greywater Storage Systems
- The
Approved Document now includes details of both horizontal and vertical flow reed bed treatment systems
- Greywater and rainwater storage systems storing water for re-use within the
building must be watertight, well ventilated and be provided with a durable and lockable access cover
to allow emptying and cleaning. Where the storage system has an overflow connection to a drain or sewer
an anti-backflow device should be fitted.
Rainwater
Drainage - H3
- As with Foul drainage, the Regulations
now specify an order of priority for methods of disposal. The effect of this is that applicants can
no longer simply chose to dishcharge rainwater to a sewer - even where a separate surface water sewer
exists. If it is reasonably practicable to use either a soakaway or watercourse - then applicants must
do so.
Order of priority
- A
soakaway
- A watercourse
- A sewer
- Soakaways
need to be designed. Details of rainfall intensity, porosity tests and storage capacity
are now included in the Approved Document, as are details of swales, filter drains and detention ponds
which may also be used.
- The effective roof areas for any given roof pitch have been
changed - for example the effective area for a 30 degree roof pitch is now 1.29 multiplied by the plan
area. Gutter sizes may therefore need to increase accordingly.
- Syphonic and eaves
drop systems are now included in the Approved Document guidance.
- Certain paved areas
(disabled access routes, common access areas and routes to waste bins) must either be free draining
(away from buildings) or pervious to allow water to soak away. If this is not possible then gullies/channels
need to be provided.
- Areas that may produce contaminated drainage need to be kept
separate for treatment. For example, areas that may be affected by petrol or oil spillage should drain
in the first instance to an oil interceptor.
Building
Over Sewers - H4
- The regulations have been changed,
so that any application for new work or underpinning within 3m of a sewer shown on records kept by the
sewerage undertaker, must be a Full Plans application.
- No building should
cover an existing manhole that serves more than one property.
- No covered length
should exceed 6m, be more than 225mm diameter or more than 3m deep
- An alternative
route for the sewer at least 3m from the building should be available so that it could (if necessary)
be diverted without affecting the building.
- Sewers should be protected during
the construction process to prevent damage.
Separate
Systems of Drainage - H5
- Rainwater drainage may only
connect to a foul sewer if a soakaway or a watercourse cannot be used (see H3) and
a separate surface water sewer is not available
- Where only a foul sewer is
available, but a surface water sewer is under construction, a separate system must be constructed up
to the point of connection to the foul sewer. This must allow the rainwater system to be later separated
and connected to the surface water sewer without unnecessary inconvenience to occupiers.
- Where
rainwater drainage from paved areas may be contaminated and could present a risk of pollution, it may
connect to the foul sewer subject to the consent of the sewerage undertaker being obtained first
Solid Waste Storage -
H6
- For domestic developments, space should be provided
for two containers (one for recyclable waste) having a combined capacity of 0.25m3 - generally an area
1.2m square would be considered acceptable. The location of the waste storage area should be shown on
the plan, and should normally allow the containers to be sited within 25m of the collection point and
30m of the dwelling. It should be possible to move containers to the collection point without needing
to pass though a building, and the pathway used should be well drained, have a maximum gradient of 1
in 12.and preferably no steps - although a maximum of 3 may be permissible if unavoidable.
- External
storage areas should be away from windows or ventilators and should preferably be in the shade or under
cover. They should also be located so as not to interfere with pedestrian or vehicle access to buildings.
- Where buildings are altered or extended, the waste storage area should be
shown on the plan and care taken to ensure that the provision is not made worse. Alternatively the storage
area could be moved
- For non-domestic developments, the waste collection authority
must be consulted for guidance on the volume and nature of waste storage required, location of storage
areas and access for removal of waste etc.